Venue rules

What each venue actually requires, read from its own documents.

Ten major exhibition venues, and the four things that decide whether a build starts on time: the approval deadline, the two-storey rules, the rigging limit and who is allowed to install it. Every figure is read from that venue’s own technical document, and where a venue publishes nothing, this says so instead of filling the gap.

VenuesStand approval deadlineTwo-storey lead timeMaximum load per rigging pointWho may install rigging
Messe FrankfurtFrankfurt6 weeks before set-up6 weeks before set-up50 or 100 kgMesse Frankfurt and contracted firms
KoelnmesseCologne6 weeks before construction6 weeks50 kgUEBERKOPF GmbH
Messe DüsseldorfDüsseldorf6 weeks before set-upAfter the stand permit50 kgMesse Düsseldorf
IFEMA MadridMadrid1 month before build-up1 month before build-up250 to 500 kgIFEMA installs all safety cables
Fira Barcelona Gran ViaBarcelona"Pre-build-up""Pre-build-up"150 to 350 kgFira official suppliers
RAI AmsterdamAmsterdamNot publishedNot published125 to 650 kgOne dedicated partner
ExCeL LondonLondonNot publishedNot publishedNot publishedExCeL rigging team or appointed supplier
Las Vegas Convention CenterLas Vegas90 days truss, 30 days multilevel30 days before move-inNot publishedThe appointed general service contractor
Dubai World Trade CentreDubaiNot publishedNot publishedNot applicableDWTC Event Services
ADNEC Abu DhabiAbu DhabiNot publishedNot publishedNot applicableADNEC Services, exclusive right

Read in full

What each venue actually requires, read from its own documents.

Ten major exhibition venues, and the four things that decide whether a build starts on time: the approval deadline, the two-storey rules, the rigging limit and who is allowed to install it. Every figure is read from that venue’s own technical document, and where a venue publishes nothing, this says so instead of filling the gap.